TimeWave Weekly Report on Electricity Industry - November 18th to 24th

November 25, 2026
에 대한 최신 회사 뉴스 TimeWave Weekly Report on Electricity Industry - November 18th to 24th

Hubei's Pankou Pumped Storage Plant Commissions First Unit, Shiyan's First

On November 20, the first unit of the 298 MW Pankou pumped storage station in Zhushan county, Shiyan, entered commercial operation, nearly six months ahead of the feasibility-study schedule. The 2.807 billion yuan plant is the first pumped storage project in the water source area of the South-to-North Water Diversion's central route and uses the existing Pankou and Xiaoxuan reservoirs as its upper and lower pools, avoiding any new dam. It is China's lowest-head mixed pumped storage scheme, with an annual output of 280 GWh, and full capacity is due by the end of the year.

 

Xinjiang's 100 MW Jinghe Molten-Salt Tower Completes 2 GW Bole-Jinghe Base

On November 22, the 100 MW Jinghe molten-salt tower CSP project in Xinjiang was connected to the grid, completing CNNC's Bole-Jinghe base, which pairs 200 MW of solar thermal with 1.8 GW of PV for a total of 2 GW. The tower uses about 16,000 heliostats and binary molten salt heated to 560 degrees Celsius, with eight hours of thermal storage that supports dispatchable output around the clock. PV capacity at the base was fully connected in 2025 and the Bole tower followed in July, making Jinghe the final piece of the complex.

 

Three Gorges Completes China's Largest Linear Fresnel CSP-PV Project in Hami

Xinhua reported on November 17 that Three Gorges' 1 GW Hami 'CSP plus PV' project is complete, China's largest linear Fresnel solar thermal demonstration. Some 260,000 mirrors covering 800,000 square metres concentrate sunlight to heat molten salt to 550 degrees Celsius, so 900 MW of PV runs by day while a 100 MW thermal unit takes over at night. At full output the project is expected to supply 2.07 TWh of green power a year and cut CO2 emissions by more than 1.63 million tonnes.

 

Qinghai Gangca Agrivoltaic Project Reaches Full Connection of First 200 MW

On November 17, the first 200 MW phase of a 1 GW agrivoltaic project in Gangca county, Qinghai, reached full grid connection. Located at 3,300 to 3,800 metres, the plant generates power above while livestock graze beneath the panels, and is expected to deliver about 361 GWh a year while avoiding roughly 515,000 tonnes of CO2. The county's grid-connected renewable capacity has now risen to 1.58 GW, consolidating its position in Haibei prefecture's 10 GW clean energy base.

 

Datong-Huailai-Tianjin South UHV Line Reaches 93% Stringing in Zhangjiakou

The Zhangjiakou section of the Datong-Huailai-Tianjin South 1,000 kV UHV AC project has strung 93.22% of its conductor and earth wire and is due to be completed by the end of the year. The 23 billion yuan scheme adds 770 kilometres of double-circuit line and four substations across Shanxi, Hebei and Tianjin. Once energised, it will carry up to 2 GW of wind from Zhangjiakou and help absorb more than 14.6 TWh of new energy a year, strengthening supply for the Beijing-Tianjin-Hebei region.

 

Greenko Commissions First Unit of India's 1,920 MW Gandhi Sagar Pumped Storage

On November 18, Greenko Group commissioned the first of nine units at its 1,920 MW Gandhi Sagar pumped storage project in Neemuch district, Madhya Pradesh. The 114.74 billion rupee scheme uses the existing Gandhi Sagar reservoir on the Chambal as its lower pool and a newly built upper reservoir, cycling 67.66 million cubic metres of water. It can run six hours at full output, generating about 3.58 TWh a year at roughly 80% round-trip efficiency, with full commercial operation targeted for June 2027.

 

Morocco's ONEE Launches Procurement for 350 MW Ifahsa Pumped Storage Plant

Morocco's national utility ONEE published the general procurement notice on November 17 for the Ifahsa pumped storage plant near Chefchaouen. The 2x175 MW scheme is backed by US$265 million from the World Bank and US$235 million from the African Development Bank. The first contract covers two 1.1 million cubic metre reservoirs, a 2.2-kilometre penstock, an underground powerhouse and a 400 kV substation, alongside a separate tender for a 62-kilometre double-circuit connection to the Oualili-Melloussa line.

 

Poland Awards 1.81 GW of Solar in Latest Renewable Auctions

Poland's Energy Regulatory Office published results on November 16 from auctions held on November 9 and 10, awarding about 1.81 GW of solar across 65 of 68 successful bids. In the above-1 MW category, winning solar prices ranged from PLN 180 to 327.77 per MWh against a PLN 389 reference price, contracting about 17.7 TWh of electricity worth more than PLN 5.5 billion. Solar again dominated the support scheme, while the hydro, agricultural biogas and biomass auctions attracted too few bids to proceed.

 

Spain's Olmedo Solar Plant Completed Under AGCO's First Virtual PPA

On November 19, Spanish developer BRUC completed and commissioned the Olmedo solar project in Valladolid province, comprising the Los Silos and El Granero plants with roughly 150,000 modules across 300 hectares. The site supplies the Spanish grid under a 10-year virtual power purchase agreement with farm equipment maker AGCO, which will receive about 150 GWh a year, equal to the consumption of some 40,000 European households. Livestock continue to graze between the panels, keeping the land in agricultural use.

 

Nigeria Adds 416 MW of Transmission Capacity with Gombe Substation Projects

On November 19, Nigeria's power minister commissioned a new 120 MVA substation at Billiri and an upgrade at the Gombe transmission station, adding 240 MW of capacity at 330 kV and 176 MW at 132 kV. The works include an additional 300 MVA transformer at Gombe, which doubles upstream capacity to 600 MVA, and a new 100 MVA unit replacing a 30 MVA transformer. The projects are expected to improve supply for more than 70,000 additional households in Gombe and neighbouring states in the northeast.